Hardy Ave paving nearing completion

Crews with Dufferin Paving were applying the first layer of asphalt on Hardy Ave last week as part of a project to repave the street in the area of the Tillsonburg Community Centre. (Jeff Helsdon Photo)
Jeff Helsdon, Editor
Hardy Ave in the area of the Tillsonburg Community Centre should be wearing a new surface just in time for the arena's upcoming busy season.
The portion of the road from the intersection with Sanders Street to the intersection in front of the seniors’ center is being repaved. The work includes replacing the surface and base asphalt.
Work started on Nov. 6 and was expected to be completed this week, weather dependent.
Costs aren’t finalized yet, but were budgeted for $275,553. Of the total, $240,000 was funded from the Federal Gas Tax Reserve, and the remainder from the Linear Infrastructure Reserve.
The project is being completed now because town staff were waiting for the completion of the community centre renovations and the construction of the new pickleball courts, as well as the results of a pavement condition assessment study.
“This approach was intended to protect the investment in the new pavement and avoid the potential for additional repairs or having to revisit the same area for further work,” said Logan Vandevyvere, Manager of Engineering.